Date | Action |
June 2019: | Measure M Funded - Notice to Proceed
|
Aug – Dec. 2019: | Secured “Letters of Commitment from Participating Agencies
|
September 2019: | SBCCOG Approved Vendor Award
|
November 2019: | First Work Order Approved by SBCCOG – for Core Ring
|
February 2020: | Second Work Order Approved by SBCCOG – for construction Phase 1 of lateral connections to SBFN sites
|
April 2020: | First City Connected to the Network
|
June 2020: | Third Work Order Approved by SBCCOG – for remaining sites not connected to the network per Metro Funding Agreement
|
June - July 2020: | Core Ring Completed and First phase of lateral connections to the network are “turned-up”
|