Timeline for Implementation

Date

Action

June 2019:

Measure M Funded - Notice to Proceed

 

Aug – Dec. 2019:

Secured “Letters of Commitment from Participating Agencies

 

September 2019:

SBCCOG Approved Vendor Award

 

November 2019:

First Work Order Approved by SBCCOG – for Core Ring

 

February 2020:

Second Work Order Approved by SBCCOG – for construction Phase 1 of lateral connections to SBFN sites

 

April 2020:

First City Connected to the Network

 

June 2020:

Third Work Order Approved by SBCCOG – for remaining sites not connected to the network per Metro Funding Agreement

 

June - July 2020:

Core Ring Completed and First phase of lateral connections to the network are “turned-up”